Commercial Depot

Perth, Western Australia · 2022 · Awarded

Engaged by Nat Fyfe's commercial trucking company to help specialise in completing the earthworks using recycled asphalt, importing road base, and preparing for a 150m concrete slab pour outside the building.

Recycled Asphalt Use

Utilized recycled asphalt to promote sustainability and cost-effectiveness in site preparation. Total amount 4400 sqm

Road Base Importation

Imported high-quality road base material to ensure a stable foundation for the slab. Total amount 5000 sqm

Site preparation

Conducted thorough site preparation, including grading and compaction, for optimal concrete slab placement.

Concrete slab pouring

Coordinated logistics for the preparation and pouring of a 150m concrete slab outside the building.

Challenges

Waste management

Challenges in managing and recycling materials efficiently on-site.

Foundation preparation

Additional work required to ensure proper foundation preparation for the concrete slab.

Communication gaps

Maintaining effective communication among all stakeholders proved challenging.

Inspection delays

Waiting for inspections from regulatory bodies impacted the timeline.