Beachridge 7A - Sewer
Awarded · 2025
We were engaged by Direct Contracting to install 330 meters of 150 sewer main in wet water conditions, including complete pressure testing and ovality ball testing. The project was successfully completed within a tight 13-day schedule.
- 01 Project planning
- 02 Deep sewer install
- 03 Quality Assurance
- 04 De-watering Solutions
Project planning
The 13-day project plan included site setup, de watering and approvals, followed by phased sewer main installation, testing (ovality and pressure) and final site restoration and handover.
Deep sewer install
The deep sewer installation involved excavating to required depths, safely shoring trenches, installing sewer mains and backfilling to specification while maintaining strict safety and quality standards.
Quality Assurance
Quality assurance was maintained through continuous inspections, adherence to design specifications, material compliance checks, and documented testing of all installed components.
De-watering Solutions
Dewatering was carried out to control groundwater and maintain dry, stable trench conditions.
Challenges
Groundwater Infiltration
Requiring effective dewatering to keep trenches dry.
Tight schedule constraints
Demanding efficient workflow and coordination to meet deadlines.
Deep excavation safety
Including trench stability and shoring under strict OH&S standards.
Utility clashes
Needing accurate service locating and coordination.
More projects
Continue through the portfolio — previous and next programmes.

HV / LV Installation
We were engaged by Tracc Civil to assist with the installation of high voltage and low voltage cables. The scope involved careful trenching, cable laying, and coordination around existing underground services to ensure safety and compliance with electrical standards.
View project
Coalseam Way - Sewer
We were engaged by Direct Contracting to install 350 meters of main sewer along Coalseam Way. The scope included deep excavation, compaction, de-watering, pipe installation and final testing within a tight project time frame.
View project